Studs & framing · Calculator

Partition Wall Materials Calculator

Enter the length and height of the new wall, the stud spacing, the doors, which sides get drywall, whether the cavity gets insulation and the finish level, and this calculator produces the complete materials list for the wall, framing, board, fasteners, tape, compound and insulation, from the same tables the separate calculators use.

It is the page to open for the most common small drywall project there is, splitting one room into two, because the questions come in a bundle and a list built from five calculators is easy to get wrong.

Partition Wall Materials Calculator

Units
ft
ft
in
Drywall on
%

Example result for the starting values. Enter your own and press Calculate.

Partition wall kit

18 studs + 6 sheets

12 ft × 8 ft, boarded both sides, 1 door, Level 4

Plates
36 ft
Screws
168
Compound
1 pail
Insulation
2 packs
Everything for the wall
Studs16 at 16 in (field, kings, jacks, cripples, nailers) → 18 with waste
Stud length92-5/8 in precut (8 ft wall)
Plates3 × 12 ft = 36 ft
Headers1 × 2 × 4, 37 in long
Face area12 ft × 8 ft − doors 19 sq ft = 77 sq ft
Drywall153 sq ft ÷ 32 sq ft × 1.1 → 6 sheets of 4 × 8 ft
Screws6 × 28 = 168, about 0.8 lb
Tape113 ft → 1 roll
Compound, Level 41.4 gal → 1 pail
Insulation77 sq ft ÷ 59.7 sq ft per pack → 2
Show the arithmetic
  1. Studs = 10 − 2 + 2 + 2 + 2 + 2 = 16 → 18
  2. Sheets = 77 sq ft × 2 sides ÷ 32 sq ft × 1.1 → 6
  3. Compound = 153 sq ft × 0.94 ÷ 100 = 1.44 gal
  • A non-load-bearing partition: it carries only its own weight and the drywall. If the wall will hold up joists or a floor, it is a bearing wall and needs headers and studs from the span tables, not this kit.
  • Fasten the top plate to the joists or to blocking between them where the wall runs parallel to the joists, and the bottom plate to the floor; on concrete, use a pressure-treated plate.
  • Floorings Calculator, our sister site, counts the baseboard and the flooring for both sides of the new wall.
  • Mineral wool or fibreglass in the cavity raises a single-stud wall from about STC 33–35 to about 36–39 (GA-600 listings); for more, see the soundproofing assembly calculator.

Shopping list

  • 18 2 × 4 studs, 92-5/8 in precut (8 ft wall)
  • 3 2 × 4 × 12 ft plate stock one pressure-treated for the bottom on concrete
  • 6 drywall sheets, 4 × 8 ft
  • 1 lb drywall screws, 1-1/4 in
  • 1 roll of paper tape
  • 1 pail of joint compound, 4.5 gal
  • 2 packs of 3 in acoustic mineral wool batts for 2 × 4 walls, 15-1/4 in wide

Understanding your result

The headline gives the two figures that decide the trip to the lumber yard, studs and sheets, and the line under it restates the wall. The tiles give the plates, the screws, the compound and, if you ticked it, the insulation.

The table is the full list in the order you will use it: studs and their length, plates, headers, then the face area after the door openings, the sheets for one or both sides, screws, tape, compound for the finish level you chose, and insulation. Each line uses the same rules as the dedicated calculator for that material: the wall stud calculator for the framing, the single wall calculator for the board layout, the joint compound coverage for the finish.

The door openings come out of the board area at the height of the rough opening, and the header length is the rough opening plus 3 in. If you only know the door size, the rough opening calculator gives the opening. The trim and flooring on both sides of the new wall are another trade; Floorings Calculator, our sister site at flooringscalculator.com, counts the baseboard.

How we calculate this

studs = field + kings + jacks + cripples + nailers (the wall stud count) × (1 + waste %) plates = 3 × wall length face area = length × height − doors × rough opening width × door height board = face area × sides; sheets = ⌈ board ÷ sheet area × (1 + waste %) ⌉ screws = sheets × screws per sheet (GA-216 pattern) compound = board × gallons per 100 sq ft for the level ÷ 100 tape = board ÷ sheet area × joint per sheet + corners (height × ends + length at the ceiling) × sides insulation = face area ÷ coverage per pack (59.7 sq ft of 15-1/4 in batts, 60.1 sq ft of 23 in)

The stud count, the screw pattern and the compound coverage are the site’s shared tables: field studs at the spacing with kings, jacks and cripples at each door; 28 screws per 4 × 8 sheet on 16 in studs; 9.4 gallons of compound per 1,000 sq ft at Level 4, pro-rated for the other levels on the coverage table. Insulation coverage is Rockwool’s published pack coverage for 3 in Safe’n’Sound mineral wool sized for 2 × 4 walls; other products list their own coverage on the bag.

The assumptions behind the numbers

Assumption Default Where it comes from
Wall type Non-load-bearing partition Scope of the site; bearing walls need span tables
Studs 16 in on centre, 92-5/8 in precuts for 8 ft IRC Table R602.3(5); standard precuts
Door rough opening 34 in × 82-1/2 in A 32 in pre-hung door
Screws GA-216 wall spacing Gypsum Association GA-216
Compound 9.4 gal per 1,000 sq ft at Level 4 USG product data
Insulation coverage 59.7 sq ft (15-1/4 in) or 60.1 sq ft (23 in) per pack Rockwool Safe’n’Sound 3 in mineral wool product data
STC with insulation About 36–39 for a single wood-stud wall GA-600 published assemblies; see the assemblies page
Waste 10% Studs and board

Assumptions last reviewed October 8, 2026.

The calculator does not count electrical boxes and wire, the door itself, casing, baseboard or paint, and it does not plan blocking for cabinets, which the plates and blocking calculator adds. The full sequence, from snapping the line to taping the last corner, is in the guide to framing a partition wall; the board count method is in the guide to counting sheets.

Two worked examples

A 10 × 8 ft wall with a 36 in door, both sides, insulated

Rough opening 38 in, 16 in studs, 4 × 8 sheets, Level 4.

  • Studs: 14 → 16 with waste, 92-5/8 in; plates 30 ft; one header 41 in long
  • Face area: 80 − 22 = 58 sq ft per side; board 116 sq ft → 5 sheets of 4 × 8
  • 140 screws, 96 ft of tape (1 roll), 1.1 gallons of compound (1 pail), 1 pack of insulation

Most of the cost of a short wall is the door and its trim, not the wall; the board and compound for both sides fit in the back of a car.

A 16 × 9 ft wall with no door, 4 × 12 sheets, Level 5, insulated

  • Studs: 15 → 17 with waste, 104-5/8 in; plates 48 ft
  • Board: 144 sq ft per side, 288 sq ft → 7 sheets of 4 × 12
  • 280 screws, 164 ft of tape, 4 gallons of compound for Level 5 (1 pail), 3 packs of insulation

Twelve-foot sheets on a 16 ft wall leave a 4 ft piece per row, which is why the waste is a sheet; on a 12 ft wall the same sheets would fit exactly.

Where to find your inputs

Length and height. The wall line on the floor and the height from floor to ceiling.

Doors. How many, and the rough opening width; a 36 in door has a 38 in opening.

Sides. Both, unless one side faces an unfinished space.

Finish level and insulation. Level 4 for painted walls; insulation if you want privacy between the rooms.

Common mistakes

  • Building on top of the finished floor without thinking about it. Decide whether the wall sits on the subfloor or the finished floor before you cut studs; it changes the stud length.
  • No fixing at the ceiling. A wall parallel to the joists needs blocking between them to fasten the top plate to.
  • Forgetting the outlets. A new wall often needs outlets by code; plan the wiring before the board.
  • Insulation after one side is boarded. Fit the batts from the open side before the second side goes on.
  • Board touching the floor. Leave 1/2 in at the bottom; the baseboard covers it.
  • Creating a bedroom without egress. A new bedroom needs an egress window and smoke alarms. Check the code.

Questions people ask

What materials do I need to build an interior wall?
For a 12 × 8 ft wall with one door, both sides boarded, about 18 studs of 92-5/8 in, 36 ft of plate, a short 2 × 4 header, 6 sheets of 4 × 8 drywall, about 170 screws, a roll of tape, a pail of compound and two packs of mineral wool if you want it quieter. The calculator lists all of it for your size.
How much does it cost to build a partition wall?
Materials for a 12 ft wall boarded on both sides typically run a few hundred dollars: lumber, about six sheets of drywall, fasteners, compound and insulation. Labour depends on the region and the finish level; the drywall cost estimator prices the board and finishing.
Do I need a permit to build an interior wall?
Often, yes. Many jurisdictions require a permit for new walls, especially if they create a bedroom (which needs egress and smoke alarms) or move electrical outlets and switches. Check with your building department before you start.
Should I insulate an interior wall?
For sound, yes. Fibreglass or mineral wool batts in the cavity raise a single-stud wall from about STC 33 to 35 to about 36 to 39 in published GA-600 assemblies. For more privacy, a second layer of board or resilient channel on one side adds more.
How do I attach a new wall to the ceiling?
If the wall runs across the joists, nail or screw the top plate to each joist. If it runs parallel and between joists, fit blocks between the two nearest joists every 24 in and fix the plate to the blocks. Fix the bottom plate to the floor framing or, on concrete, with concrete screws through a pressure-treated plate.
How long does it take to build a partition wall?
Framing a 12 ft wall with a door is a day for one person; hanging the board both sides is half a day; taping and finishing to Level 4 is four or five days, mostly drying time. Call it a week from layout to paint for a careful DIYer.
Embed this calculator on your site

Paste the code into any page. It is free to use; the only thing we ask is that the credit link under the calculator stays.